    Senate Passes Bipartisan Permitting Reform Bill, 62-33

    November 26, 2026Senate Roll Call Vote 270, November 19, 2026Federal3 min read

    November 26, 2026

    On November 19, 2026, the US Senate voted 62-33 to pass the Senate permitting reform bill, H.R.2347, with an amendment that swaps out the House-passed text for the Bipartisan American Affordability and Jobs Act of 2026. The legislation would rework parts of the federal permitting process under the National Environmental Policy Act, the Clean Water Act, and the Federal Power Act, and it would set new cost rules for data centers. As of November 26, 2026, it wasn't law. The House would have to agree to the Senate's text, and the President would have to sign it.

    Key Takeaways

    • The Senate passed the permitting reform bill 62-33 on November 19, 2026.
    • The bill would set new NEPA decision deadlines and limit when, and by whom, NEPA challenges could be filed.
    • It would change how states handle Clean Water Act certification and extend some discharge permit terms.
    • It would rewrite the Federal Power Act's transmission siting provision for lines of at least 230 kV.
    • Under its stated policy, data center owners and operators would bear the full cost of the power and grid infrastructure built to serve them.
    • As of November 26, 2026, the House had not agreed to the Senate's text, and none of these changes were in effect.

    What the Senate Permitting Reform Bill Would Do

    H.R.2347 began as the House-passed Survivor Justice Tax Prevention Act. The Senate's engrossed amendment, which runs 488 pages, replaces that text in full with the Bipartisan American Affordability and Jobs Act of 2026. That's why a tax bill number now carries a permitting overhaul. The legislation is organized in three divisions.

    Division A, from the Environment and Public Works side, covers NEPA, the Clean Water Act, the Endangered Species Act, and nuclear licensing. Division B, from Energy and Natural Resources, covers transmission, energy permitting, and historic preservation. Division C keeps the bill's original survivor-justice tax exclusion. Taken together, the permitting bill would amend several federal environmental laws to speed agency decisions, mainly through new deadlines.

    Only the text the Senate actually passed matters here. Earlier versions, including a November 7 substitute and a separate Senate bill, aren't part of it. Neither is managers' amendment No. 7030, which didn't make it into the passed text after Senator Jeff Merkley objected.

    NEPA Deadlines and Environmental Reviews in the Permitting Process

    Section 1106 would amend NEPA's deadline provision (42 U.S.C. 4336a(g)). An environmental assessment would be due within 1 year, followed within 7 days by a finding of no significant impact or a notice that a full environmental impact statement is coming. An impact statement would be due within 2 years, with the record of decision 45 days after it's published.

    Other agencies would then have 90 days (participating) or 120 days (non-participating) to decide their outstanding permits. That piece matters for multi-agency energy projects, where one late permit can hold up everything else. Some of the outer 1-year and 2-year limits may overlap with current law; the follow-on decision deadlines are this bill's additions.

    The comment period on an impact statement would run 45 to 60 days, extendable by agreement to no more than 75. Under Section 1109, agencies would have 60 days to say whether an application is complete. The bill doesn't add page limits to assessments or impact statements. The only page cap flagged in the text is a 20-page limit on the "record of stakeholder engagement."

    What happens if an agency misses a deadline? The project sponsor could go to court, and the court "shall provide injunctive relief, as appropriate." The text doesn't provide a damages remedy.

    Limits on NEPA Court Challenges and Remedies

    Section 1110 would add a new NEPA section 111. A NEPA challenge would be barred unless filed within 150 days. The challenger would need to have submitted a substantive comment on the issue and would have to allege a direct, actual or imminent injury. Those are limits on who can sue and when, not a general rewrite of standing.

    The remedy rules matter just as much. The default would be remand without vacatur: the decision goes back to the agency without being voided or enjoined, the agency gets no more than 180 days to fix it, and the permit stays in effect meanwhile. A preliminary injunction would require a likely violation of a law other than NEPA or the National Historic Preservation Act.

    For project sponsors, that combination would shorten the window for NEPA litigation and make it harder for a NEPA flaw alone to stop work. For groups that challenge projects, the comment requirement would put more weight on taking part early in the environmental reviews.

    Clean Water Act Certification Under the Permitting Bill

    Section 1202 would change state water quality certification under Clean Water Act section 401. A state could deny certification only on "clear and convincing evidence" that no reasonable condition would allow compliance, or that required information is still missing. Any conditions would have to be shown, by the same standard, to be "necessary" and "the least burdensome." Review would be limited to CWA sections 301, 302, 303, 306, and 307.

    A state that doesn't act within 1 year would waive the requirement, and that window would shrink to 9 months for natural gas pipeline certificates and interstate transmission lines. A court couldn't review an affirmative waiver. Section 1203 would extend clean water discharge (NPDES) permit terms from 5 years to 10. Section 1205 would still allow an injunction against section 404 permits where there's an "imminent and substantial danger to human health or the environment."

    Transmission and Natural Gas Provisions in the Legislation

    Section 2101 would rewrite Federal Power Act section 216, the transmission siting provision, for lines of at least 230 kV. Costs would be allocated by cost causation and "roughly commensurate with the benefits," and customers who get no benefit, or only a trivial one, couldn't be charged against their will.

    Section 2102 targets upgrades to existing lines. Reconductoring and capacity upgrades within an existing right-of-way, or up to a quarter mile beyond it, wouldn't trigger NEPA or historic preservation review. Covered natural gas pipeline modernization under Natural Gas Act section 7(i) would get the same treatment. For energy infrastructure that's already built, upgrades like these could take a full federal environmental review out of the picture.

    Data Center Cost Rules in the Bipartisan Bill

    Data centers get their own set of rules. Section 2107 states a policy that "computational load" owners and operators "bear the full cost of any electric service that they require and the full cost of any infrastructure built to serve them." That definition reaches AI, crypto mining, and other data-center computing. FERC would have 90 days to revise its transmission pricing policy, then 1 year after the proposed rule to issue a final rule.

    A new Federal Power Act section 229 would set a "Ratepayer protection floor." No retail incremental cost could be charged to any customer other than the computational-load owner or operator, and the utility would have to require financial assurances before it builds. The floor would apply only to data centers that connect on or after enactment. Section 2114 would direct the Energy Information Administration to collect data on these sites, and Section 2117 would create a DOE community assistance program within 180 days.

    Sponsors have described these provisions more loosely. Senator Shelley Moore Capito's November 9 floor remarks, as prepared, said the bill "will make potential data centers pay their own way," and a November 5 fact sheet from Senator Martin Heinrich's office described it as directing FERC to require rates that make large data centers pay. Both came before final passage. The bill's own words, quoted above, are what would carry legal effect.

    The 62-33 Vote on the Permitting Reform Bill

    The roll call (vote 270) opened at 9:30 p.m. ET, and the bipartisan permitting reform bill passed at 10:02 p.m. The yes votes came from 47 Republicans, 14 Democrats including Chuck Schumer, and Angus King. Thirty Democrats, including Jeff Merkley, voted no, along with Josh Hawley, Mike Rounds, and Bernie Sanders. Five senators didn't vote: Bill Cassidy, John Cornyn, Mitch McConnell, Chris Murphy, and Tommy Tuberville.

    The vote has drawn attention on X and in national coverage, including NPR's report.

    What Happens Next in the House

    Because the Senate amended a House bill, the House has to agree to the Senate's version before the legislation can go to the President. Capito's November 19 release urged the House to pass it "expeditiously." On November 24, 2026, a message on the Senate action was sent to the House. As of November 26, 2026, the House had not agreed to the Senate's text. The House Committee on Rules was scheduled to meet on November 30, 2026, at 4:00 p.m., in H-313 of the Capitol, to consider the Senate amendment.

    As of November 26, 2026, neither step had happened, so existing permitting rules remained in place. The bill's provisions, including the NEPA deadlines and the ratepayer protection floor, would only start to matter after enactment.

    Who the Permitting Bill Could Affect

    The reach is broad. Developers of infrastructure and energy projects that need federal environmental reviews would face new deadlines on the agency side and new limits on court challenges. States would work under a tighter Clean Water Act section 401 standard and timeline. Transmission developers and natural gas pipeline operators would see changes to siting, cost allocation, and review of upgrades.

    Data center owners and operators, and the utilities that serve them, would be looking at the cost policy, the financial-assurance requirement, and a coming FERC rulemaking. Community groups and others that challenge permits would see a 150-day filing window and new comment and injury requirements.

    Practical Considerations for Energy and Infrastructure Projects

    Steps businesses commonly consider include the following. The right approach depends on your facts.

    • Mapping pending and planned energy projects against the proposed NEPA and Clean Water Act timelines.
    • Weighing how the 150-day filing window and the remand-without-vacatur default could affect litigation risk on project approvals.
    • For data center developers and utilities, reviewing how the ratepayer protection floor and financial-assurance requirement would apply to new interconnections.
    • Identifying transmission or pipeline upgrades that might fall within the existing right-of-way provisions.
    • Tracking House action, since nothing changes unless the House agrees and the President signs.

    How these provisions would apply depends on the project, its timing, and the final text, so they're worth discussing with counsel. Questions can be directed to Cogent's Energy Practice: Transactions, Finance and Regulatory, including attorney Thomas Gross, and to our Corporate and M&A team for project development and transactions.

    Contact Us Now

    For questions about the Senate permitting reform bill or energy and infrastructure projects, contact Cogent Law or call 202-644-8880.

    Related Practice Areas

    Talk to Cogent Law

    Have questions about how this update may affect your business?

    For questions about the Senate permitting reform bill or energy and infrastructure projects, contact Cogent Law or call 202-644-8880.

    Legal Disclaimer

    This article provides general information only. It is not legal advice. Reading this article does not create an attorney-client relationship. As of November 26, 2026, H.R.2347 had passed the Senate with an amendment and was not law; its text and status may change.

    Speak With Counsel

    Relevant Cogent Law attorneys

    Businesses following this development may want to speak with counsel familiar with this area.